State of Under Construction Road Works in Bengaluru – 2025

February 19, 2025 Vaidya R

A week back, OpenCity conducted a survey to crowd-source all the under construction road projects in Bengaluru. The goal was to first see how many such projects are lying around in the city and then situate them against the current frenzy for tunnel roads and elevated corridors across the city. A body with a poor record on completing road projects is not going to have much success in completing similar projects that it plans to take up now.

The survey threw up 20+ such projects. While most are flyovers, underpasses and railway bridges that have been waiting to see the light of the day for years, there were some curious ones where pillars were left on the side even though the planned bridge was completed. In one case an existing railway bridge was brought down with no sign of the promised new one.

List of projects

Sl No.Project NameDescriptionStartedPlanned Duration
1Ullal/University Quarters UnderpassUnderpass abandoned after shifting a temple and digging up one side of the road next to University Staff Quarters.March 20212 years
2Annapoorneshwarinagar/Nagarabhavi BDA Complex UnderpassUnderpass abandoned after digging up area acquired from Nagarbhavi BDA complex as well as KLE Institutions. Many trees were chopped for this.March 20212 years
3Peenya UnderpassUnderpass abandoned after finishing one half of it on Peenya side.2016None given.
4Ejipura FlyoverFlyover languishing since many years, now repeated tendering is happening and the latest deadline is December 2025.201730 months
5Dommasandra FlyoverPillars constructed and left with no sign of completion. Residents and commuters now left in the lurch.September 2020Not given
6Katamnallur Gate FlyoverThis is technically an NHAI project but has become a major bottleneck. November 20231 year
7Yelahanka Doddaballapur Road FlyoverPillars constructed and little else happening. Completion set for 2026 now.January 202218 months
8Hebbal Flyover RampMultiple deadlines have come and gone for the ramp from KR Puram side to the city. Has become a scene of regular bottlenecks.April 20248 months
9Kerekodi/Veerabhadranagar FlyoverOne ramp pending for more than a year while work has completely stopped. 4 pillars, 3 spans and one ramp done. Congestion has increased due to this construction.August 202015 months
10Jakkur Railway OverpassBeen in the works for many years now. Might see the light of the day this year.20121-2 years
11Central Silkboard Double decker flyoverThe Flyover, combined with Metro work – yellow, followed by blue line is going on for a decade, and no sign of completion. While the part from Jayanagar to HSR is done, the other side is taking a long time.20211 year
12Yelahanka Railway UnderbridgeThis is a much pending work to build an underbridge under the Yelahanka Railway Station to join Old town and new town.February 2021None given.
13Panathur S-Cross UnderpassIn the news for many years, residents even staged a protest. Pace continues to be slow and congestion is common.October 2020None given
14Carmelaram ROBRailway Overbridge needed for a railway gate. Took a long time to start, is stuck again with land acquisition issues.202318 months
15CDP Road 150 ftWidening of the road to New Horizon. Progressing at a slow pace, has almost stopped now despite promises of fast-tracking.Not clear.
16Pipeline Road bridgeUnderpass under the flyover is done, but a bridge across the Vrishabhavathi was promised for connectivity to the entire pipeline road, which is pending for years.2020Not given
17Pipeline road underpassExpected to connect Pipeline road to ORR across a busy junction. Dug up and left. This was part of the underpasses taken up with Ullal and Annapoorneshwarinagar in RR Nagar constituency and abandoned together.March 20212 years
18Varthur road circle flyover.Pillars constructed and abandoned. Nobody knows why it was planned in the first place.202318 months
19Rajarajeshwari Nagar Arch FlyoverPillars under the Arch are done, and abandoned after that. Has now become a major bottleneck.20222 years
20ISRO-Wind TunnelService Road done and then left. Nobody can use the service road either. No sign of actual underpass for many years.Not started
21Vijayanagar Railway overbridge Existing bridge was destroyed without a clear reason. Approval from Railways is now awaited to start the construction again. This was a major road to connect Goripalya towards Vijayanagar. Construction is stalled for more than 3 years, with no sign of progress. People have to take longer routes due to this.June 2023No deadline given

With twenty one projects languishing with no signs of completion, it is not hard to guess what would be the state of the current tunnel roads or elevated corridors after five years.

Large projects continue to be planned in Bengaluru by BBMP. Pic: Ojas Shetty

The Government of Karnataka spoke about new projects with Rs. 1 Lakh Crore being earmarked in Bengaluru with the largest chunk going to the Tunnel Roads. As a recent article pointed out there are already large holes in the planning that has gone into the tunnel roads project which portends the eventual fate of the project.

Finishing the long list of pending projects can relieve a lot of congestion in the city. But then the vision of the planners needs to be to fix congestion and not just build new infrastructure. The former will require planning, in the form of empowering the Bengaluru Metropolitan Land Transport Authority (BMLTA), having a working Master Plan, an elected Urban Local Body among other such simple measures. The latter, only lots of money to “start” such projects.

The locations of these projects can be viewed on the map below.